First Commissioning
19
5 First Commissioning
WARNING
W4.0002
Danger to life through electric shock
Damaged power cable
An electric shock can cause burns, cardiac arrhythmia, respiratory arrest,
as well as cardiac arrest.
Never use a damaged power cable to connect the device to the
mains!
Check the power cable and the plug for any damage before use.
NOTICE
N11.0002
Setting up the device
Disconnecting the device from the mains
A separation of the device from the mains must be possible at any time.
Set up the device in such a way, that the connection for the power
cable is always easily accessible.
NOTICE
N12.0004
Setting up the device
Vibrations during operation
Depending on the operating mode of the device, slight vibrations may
occur.
Set up the device only on a vibration-free, plane and stable surface.
Before first commissioning the sieve clamping unit must be installed.
The AS 200 control is suitable for test sieves of 100 mm to 203 mm outer diameter. Up to 23
fractions (22 test sieves plus collecting pan with a height of 25 mm), or 11 fractions (10 test
sieves plus collecting pan with a height of 50 mm) can be clamped.
NOTICE A high number of test sieves can significantly increase the total weight of the load
(sieve stack and sample material). Make sure not to exceed the maximum payload of 9 kg.
Different sieve clamping units and lids are available for the test sieves.
"economy"
"standard"
"universal standard"
"comfort"
"universal nass"
for sieve Ø
for sieve Ø
for sieve Ø
for sieve Ø
for sieve Ø
100 203 mm
200/203 mm
100 203 mm
200/203 mm
200/203 mm
Fig. 4: Types of the sieve clamping unit