POWERING ON FOR THE FIRST TIME
If present, set the “1/0” switch to “1” and wait for a few seconds. Check that
the display is turned on and the UPS enters "STAND-BY" mode.
Check that no error messages appear indicating that the input cables do not respect the correct cyclic phase sense (for
three-phase input only). If error messages appear, perform the following operations:
Switch off the UPS by moving the “I/0” switch to “0” (if present), and open all the input and output disconnecting switches.
Wait for the display to go off.
Open the battery fuse holders.
Open all the protective devices upstream from the UPS
Remove the panel covering the input terminal board
Correct the position of the input wires so that the phase direction is respected.
Close the panel again
Repeat the power-on operations including the "preliminary operations"
Press to enter the start menu. Choose Yes when prompted to confirm.
Press to confirm and wait for a few seconds. Check that the UPS is set
with the load powered by the inverter.
Open the input switch (SWIN) and wait for a few seconds. Check that the
UPS goes into battery-powered mode and that the load is still powered
correctly. A beep should be heard approximately every 7 seconds.
Close the input switch (SWIN) and wait for a few seconds. Check that the
UPS is not in battery-powered mode and that the load is powered correctly
by the inverter.
To set the Date and Time, access menu 8.6.7 (see “Display menus”). Use
the up/down arrows (↑↓) to set the desired value and then confirm with the
key to move to the next field. To save the new settings, go back to the
previous menu by pressing the key.