3�4 Lubrication and Maintenance Schedule
The inspection schedule can be carried
out according to the working hour or the
planned date, whichever comes earlier�
Each inspection shall not only cover the
planned tasks but also all the ones carried
out previously�
For the maintenance of the engine, refer to
the specic operating manual provided by
the engine manufacturer�
-- The time interval specified in this
sch edu le app lie s t o th e “g en era l
situation”, which is decided by the
experience gained during using the
lubricating oil and by the suggestion
provided by the supplier� In adverse
operation conditions such as excessive
dust, corrosive air, abnormal outdoor
temperature, massive load, extreme
frequent or long-time operation cycle,
can shorten the lubrication interval�
Before there is sufficient experience
for self-made schedule, the schedule
provi ded in th is chap ter sha ll be
followed�
-- The following problems found in the
routine inspection such as over-heat
in bearing and lining, moving parts
looseness, and rust accumulation in
moving parts, indicate that there is
lack of lubrication, which requires
shortening the lubrication interval of
problematic parts�