ELECTRICAL SYSTEM
15. Every 200 hours:
CHECKING ELECTROLYTE LEVEL
IN BATTERIES
1. Undo the plugs and check the electrolyte level in all cells.
2. Top up using distilled water until the level is 10-15 mm above the plates.
16. Every 200 hours:
CHECKING CHARGE
STATE IN THE BATTERIES
Note! Every 200 hours applies to gensets and the like.
Other installations every 1,200 hours.
- Check specific gravity using a battery electrolyte tester.
In a fully charged battery it should be:
1,280 at +20°C
1,294 at 0°
1,308 at -20°C
- If the specific gravity is below 1.20, the battery must be charged.
A discharged battery freezes at -5 °C.
Avoid boost charging. This will damage the battery in the long term.
17. Every 200 hours:
CLEANING BATTERIES
Note! Every 200 hours applies to gensets and the like.Other installa-
tions every 1,200 hours.
1. Clean batteries, cables and cable terminals.
2. Check that all cable terminals are well tightened.
3. Grease posts and cable terminals using petroleum jelly.

Table of Contents

Questions and Answers:

Question and Answer IconNeed help?

Do you have a question about the Scania D11 and is the answer not in the manual?

Scania D11 Specifications

General IconGeneral
BrandScania
ModelD11
CategoryEngine
LanguageEnglish

Related product manuals