6.5.2 Shutdown operating procedure
1. Prepare the solution carefully mixing the bottle of
SC1 in about 15 lit of unchlorinated water.
2. Connect the 3 hoses to the pre-pump and
watermaker as indicated above, and dip them in
the solution.
3. Check they are well dipped in the solution and
don't inhale air.
Hoses under the free water surface