EasyManua.ls Logo

Securlift Secur3 - Insulation Test

Securlift Secur3
70 pages
Print Icon
To Next Page IconTo Next Page
To Next Page IconTo Next Page
To Previous Page IconTo Previous Page
To Previous Page IconTo Previous Page
Loading...
follows: IM_SEC3_02.01_en.docx
21/70
Insulation test
Preliminary operation
Insulation test have to be performed after complete and correct functional test of the lift have been
made.
Position the car between two floors and check that all doors are closed.
Check that AM circuit breaker (on control panel) is closed.
Switch off the mains (both power and light supply).
Remove all yellow/green wires from earth bar, except those connected to metal parts and to earth
disperser.
Disconnect yellow/green wire from terminal 100, in controller and in car connection box.
Disconnect yellow/green wire from terminal 100 in the emergency battery drive SEC-3EBD
Remove connector P8 on SEC-3Q board.
Remove connector CAL on SEC-3FDR board.
Remove all connections from inverter (if provided).
Remove all connections between controllers (if multiplex lift group) and perform complete test
procedure on every single lift.
Insulation measures
By a 500V insulation tester, check resistance values between terminals according following table.
Measured values (in megaOhm) must be higher than 0.5 MΩ.
POWER
CIRCUIT
M1
M4 (U)
LIGHT
CIRCUIT
LC/L
LV/L
* DOOR
CIRCUIT
MPA/1
ALARM
CIRCUIT
CAL/6
SAFETY
CIRCUIT
SQ1/3
SQ2/9
100
>0,5
>0,5
>0,5
>0,5
>0,5
>0,5
>0,5
>0,5
>0,5
>0,5
>0,5
>0,5
>0,5
>0,5
>0,5
(*) Note: with 230VAC or mains voltage door operator supply do not run the test between
POWER CIRCUIT and DOOR CIRCUIT.
Restore all modified connections when finished.