SECTION 1 INTRODUCTION
1.1 TOOLS
The following hand tools are required for the Installation:
• Standard service engineers tool kit.
• Electric drill motor and assorted bits.
1.2 PRE-INSTALLATION CHECKS
Prior to beginning installation it is recommended to inspect the site and verify
that the X-ray room complies with requirements such as:
• Space Requirements to allow installation and system movements must
consider the maximum dimensions and travels of the equipment.
Maximum Height 2720 mm
Maximum Width 2260 mm
Maximum Length 1400 mm
• Conduits and walls are ready to install the system.
• Electricity installation:
Main Supply: Single phase, 50 / 60 Hz
115 / 208 / 230 / 240 V~
Minimum power input required: 400 VA
ACCORDING TO THE MDD/93/42/EEC, THIS UNIT IS
EQUIPPED WIT H EMC FILTERS. THE LACK OF THE
PROPER GROUNDING MAY PRODUCE ELECTRICAL
SHOCK TO THE USER.