Guardian Field Support Manual – Section 2
82
7.1 FINAL QA
Final QA
At the end of the installation a final Quality Assurance (QA) check is required to be conducted.
You must check the following:
1. All components of the system have been installed.
2. Cables are zip tied, excess lengths are removed, and the cables do not interfere with the
normal function of the vehicle.
3. Cables are hidden from view (as much as possible).
4. All vehicle pieces and fasteners are returned to the correct place on the vehicle.
5. The system powers down when the key is turned off.
6. All rubbish has been removed from the vehicle and disposed of appropriately.
7. You have removed all your tools.
8. You have taken the photos as required in the installation checklist.
9. You have completed and signed the installation checklist.
10. You have retained all the installation paperwork and photographic evidence of the
install.
11. You have notified the site manager that the truck is ready for release and they have
signed off on the checklist.
INSTALLATION IS NOW COMPLETE

Questions and Answers:

Question and Answer IconNeed help?

Do you have a question about the Seeing Machines G2-SY-CON2-1001272 and is the answer not in the manual?

Seeing Machines G2-SY-CON2-1001272 Specifications

General IconGeneral
BrandSeeing Machines
ModelG2-SY-CON2-1001272
CategoryMeasuring Instruments
LanguageEnglish

Related product manuals