508.366.1488 | www.semshred.com
10
Figure 1. System interconnections
Startup and Operation
Important: Most problems occur during the first hours of operation. These can be eliminated by careful
review of this operation manual.
Warning: Use only intended materials in the disintegrator (see Acceptable Materials and Feed Rates, page
13) or jamming may occur. To clear jams, see Troubleshooting, page 41.
New Operators: It is recommended to give new operators approximately two hours for a break-in period
beginning with a slow feed rate to familiarize themselves with the unit.
Pre-Start-Up Procedure
• Familiarize yourself with all controls and button locations.
• Familiarize yourself with the acceptable media for this unit.
• Confirm the flex vacuum hose and communication cable connection between vacuum fan system
and the SSD2-HS disintegrator.
Vacuum fan system
(waste evacuation system)