Fasten the circuit breaker to the rear wall of the switchboard panel with 4 screws (included
in the scope of delivery) with a tightening torque of 8.6Nm.
2. Screw the busbars/cables of the main conductor paths to the connections of the circuit
breaker (for tightening torques, see table Tightening torques at a glance (Page154)).
Note the operating instructions of the relevant connection system (see Chapter Reference
documents (Page10)).
3. Mount the prescribed insulation accessories.
You will 󹪝nd information about the insulation measures in Chapter Isolating distances and
insulating equipment (Page147). When mounting the insulation accessories, follow the
relevant Operating Instructions (see Chapter Reference documents (Page10)).
4. Mount the armature plates for protection from short-circuits (see Chapter Armature plates
(Page149)).
Note
Fixed-mounted circuit breakers do not need to be grounded.
Connection and commissioning
5.2Mounting and connecting the device
3VA27 molded case circuit breakers & 3WL10 air circuit breakers
Equipment Manual, 10/2023, L1V30499596002-03 163