Loading...
Accessories to be tested Method
Closing coil (CC) with
actuator module COM ACT
1. Supply power to the ETU with auxiliary voltage at the Breaker Connect module.
2. Switch on the contacts of the actuator module.
3. Charge the springs.
4. Choose item "Close CB" in the menu of ETUs of the 6-series.
Result: The circuit breaker closes correctly. The behavior and the signals of the auxiliary
switches are normal.
NOTE: The test can be conducted if voltage is applied to the protection enable and to the
coils.
Interlocking for circuit breakers in
the open position (cylinder lock or
padlock)
1. Open the circuit breaker.
2. Hold the pushbutton for opening pressed or press the cover onto the mechanical
pushbutton while you hook in the padlock.
3. Turn the key and then remove it.
4. Attempt to close the circuit breaker.
Result: Both manual and electrical closing are prevented.
Auxiliary contacts of the circuit
breaker
1. Connect the auxiliary contacts to the corresponding signaling circuits.
2. Perform a few close and open operations on the circuit breaker.
Result: Signaling performed normally.
Circuit breaker position in the guide
frame. Position signaling contacts
PSS for signal: CB inserted, test posi‐
tion, and disconnected position
1)
1. Connect the auxiliary contacts to the corresponding signaling circuits.
2. Put the circuit breaker into the following positions: CONNECT, TEST, and DISCONNECT.
Result: The signals caused by each operation are correct.
Mutual mechanical interlocking be‐
tween circuit breakers installed side
by side or one above the other
Perform the function tests.
Result: The interlockings function correctly.
Racking of the circuit breaker in the
guide frame
1)
Move the circuit breaker out of and into the guide frame several times.
Result: In the CONNECT position, the circuit breaker is correctly connected. No particular
resistance is felt during the 󹪝rst turns of the crank handle.
Auxiliary solenoids power supply Check the installation: The value of the auxiliary voltage of the auxiliary solenoids must
be between 85% and 110% of the rated voltage for the auxiliary coils.
CB Bus Module Supply power to the ETU.
Result: Check that the LEDs that signal readiness on each of the installed accessory items
light up.
Check that the communication cable for the local bus on the ETU is activated.
External current transformers WARNING!
Before this test, the circuit breaker must be in the OPEN position and, if it is a withdraw‐
able breaker, in the DISCONNECT position.
Connect a 1-pole neutral transformer / summation current transformer to the auxiliary
conductor terminal system. Set the parameters and select the con󹪝guration in accord‐
ance with the ETU.
Result: No alarm pending on the ETU.
1)
Withdrawable breaker only:
Connection and commissioning
5.5Commissioning
3VA27 molded case circuit breakers & 3WL10 air circuit breakers
Equipment Manual, 10/2023, L1V30499596002-03 181

Table of Contents

Other manuals for Siemens SENTRON 3WL10

Related product manuals