6. Repeat steps 4 and 5 for other interconnections.
7. When you have created all interconnections, click "Save".
The interconnections will be saved in the project.
Download
The schedule for the FOUNDATION Fieldbus is calculated automatically during the download
to the FF devices.
Additional information
ā— Online help for SIMATIC PDM
Engineering
4.2 Configuring
FOUNDATION Fieldbus
32 Commissioning Manual, 03/2013, A5E03880935-02

Other manuals for Siemens SIMATIC PCS 7

Questions and Answers:

Question and Answer IconNeed help?

Do you have a question about the Siemens SIMATIC PCS 7 and is the answer not in the manual?

Siemens SIMATIC PCS 7 Specifications

General IconGeneral
BrandSiemens
ModelSIMATIC PCS 7
CategoryControl Systems
LanguageEnglish

Related product manuals