16. From the base controls, carefully raise the platform.
Refer to Section 2.5-3 for procedure to raise the
platform.
17. Unlatch and carefully swing down the
maintenance support. Refer to Section 2.2-13 for
procedure to properly position the maintenance
support.
Warning
The maintenance support must be used during
inspection and maintenance or repairs are to be
performed within the lifting mechanism.
Failure to avoid this hazard could result
in death or serious injury.
18. From the base controls, carefully lower the platform
until the scissor assembly is firmly resting on the
maintenance support. For procedure on how to
lower the platform refer to Section 2.5-4 .
19. Inspect all hoses, fittings, wires, cables, valves,
etc. for leaks, loose or missing parts, hidden
damage and foreign material.
20. Raise the platform until there is an adequate
clearance to swing up the maintenance support
and lock in position.
21. Raise the platform to the maximum extension
height.
Warning
Be aware of overhead obstructions or other possible
hazards around the machine when lifting.
22. Fully lower the platform.