EasyManua.ls Logo

Snorkel UL40 - Pre-Operation Safety Inspection Checklist

Snorkel UL40
115 pages
Print Icon
To Next Page IconTo Next Page
To Next Page IconTo Next Page
To Previous Page IconTo Previous Page
To Previous Page IconTo Previous Page
Loading...
Page 2 - 11UL25/UL32/UL40
CONTROLS/PRE-OPERATION
PRE-OPERATION SAFETY INSPECTION
NOTE: Carefully read, understand and follow all safety rules, operating instructions, labels
and National Safety Instructions/Requirements. Perform the following steps each day be-
fore use.
1. Check that all 4 outriggers are properly installed.
2. Check that the base is level.
3. AC units: Connect the power unit plug to an approved extension cord.
4. DC units: Verify that the batteries are charged.
5. Perform the safety interlock tests.
6. Check for external damage to the mast.
7. Check the level of the hydraulic uid with the platform fully lowered using the following proce-
dures;
Remove the reservoir cap and check the uid level on the dipstick.
Add hydraulic uid if necessary. Oil should be visible on the end of the dipstick.
8. Check that the uid level in the batteries is correct. Refer to “Battery maintenance”.
9. Check that all guardrails are in place and all fasteners are properly tightened.
10. Inspect the machine thoroughly for cracked welds and structural damage, loose or missing
hardware, hydraulic leaks, damaged control cable and loose wire connections.

Table of Contents

Other manuals for Snorkel UL40

Related product manuals