8.1. Start-up
Before start-up, ensure that the batteries are fully charged. Before using the
UPS for the rst time, please check the battery capacity and the charging
settings. Make sure that you charge the batteries until the battery capacity
percentage shown on the LCD of the UPS is 100% ( ).
The congurable internal battery string quantity ranges from 16 to 22.
Please make sure that the actual quantity of battery strings are the same as
congured on the LCD. Set up the corresponding charge current based on
the total battery amp-hour.
If the UPS connects to an inductive load, the inrush current (initial surge
current) may restart the inverter. To avoid this situation, please turn on the
inductive load in bypass mode before starting up the inverter.
8.1.1. Start-up with AC Input
1
Verify if the UPS’s input meets with N, L & G of the utility AC power works
normally.
2
Switch on the input protective device (see Figure 7-1) installed between the
UPS and the utility AC power. After that, the UPS will enter into the Initial Setting
Screen (please refer to 9.1 Initial Setting Screen for more information).
3
Press and hold the ON/ OFF button (
) for 3 seconds to start up the UPS.
Release the button after you hear one beep and the UPS will start up. After the
UPS performs self-diagnosis, the UPS will run in ON-LINE mode.