Power Control
The Grid Control option may be disabled. Enabling it opens additional options in the
menu.
The Energy Manager option is used for setting power export limitation, as described in
the
Export Limitation Application Note
, available on the SolarEdge website at:
https://www.solaredge.com/sites/default/files/feed-in_limitation_application_note.pdf.
Step 3: Verifying Proper Activation and
Commissioning
1. Select Information and verify that the correct firmware versions are installed on each
inverter.
2. Select Status and verify that inverter is operating and producing power.
3. Verify that additional configurations were properly set by viewing the relevant
Status screens.
4. Verify that the green inverter LEDis steadily lit.
Your SolarEdge power harvesting system is now operational.
Configuring Communication with Other Devices
If the above devices have not been auto-detected during system activation, configure
them as explained below.
To set up communication with an LGChem battery:
1.
Run SetApp and select Commissioning > Site Communication.
2.
From the Site Communication screen, select RS485-1 > Protocol > Modbus (Multi-
Device).
3.
Return to the previous screen and select Add Modbus Device > Battery.
4.
If installing a second LG Chem Prime battery,
a. Select Add Modbus Device > Battery again.
b. Set the Device ID to 14.
5.
Verify the battery information by selecting Battery 1 > Battery Information.
To set up communication with the SolarEdge Energy Bank:
1. Run SetApp.
Chapter 6: Activating, Commissioning and Configuring the System 43