5 Commissioning
5.1 Inspections prior to commissioning
Check the following points before you start up the inverter:
■ All the necessary earth lines have been connected (see 4.7.4 “Earthing the inverter”).
■ Make sure the polarity of the PV generator connection is correct.
5.2 Commissioning
If the inverter is being commissioned the initial setup will start automatically. This proce-
dure must only be carried out once as part of the commissioning process. I
Requirements
■ Correctly connected DC supplies (AC connection is not required)
■ Suf cient solar irradiation
NOTE
■ Thoroughly read the manual before starting initial start-up. Contact your grid op-
erator or the SolarMax Service Centre if you have any doubt regarding the settings
you must select.
■ You can restart initial start-up on the graphics display by pressing at any time.
Procedure
1. Switch on the DC disconnector. The “Initial Setup” menu will be displayed on the
graphics display.
– Select the display language.
– Select the country setting.
CAUTION
Entering the country incorrectly may lead to problems regarding inverter operation and
to the withdrawal of the operating license by the respective grid operator.
– Enter today’s date. The inverter saves the date entered as the initial start-up date.
– Enter the current time.
– Click
to con rm the entries.
Step 2: only for country settings “Germany”, “Great Britain” and “Italy”:
2. Determine the “Plant type” and/or the “Standard”.