5. Commissioning & Shutdown
5.1 Preparation of Commissioning
Ensure all the devices are accessible for operation, maintenance and service.
Check and confirm that the inverter is firmly installed.
Space for ventilation is sufficient for one inverter or multiple inverters.
Nothing is left on the top of the inverter or battery module.
Inverter and accessories are correctly connected.
Cables are routed in safe place or protected against mechanical damage.
Warning signs and labels are suitably affixed and durable.
5.2 Commissioning Procedure
Step 1: Measure DC voltage of PV strings and battery and ensure the polarity is correct.
+
-
Step 2: Measure AC voltage and frequency and ensure they are within local standard.
Step 3: Switch on the external AC breaker to power on the inverter control board.
(Bluetooth signal available)
Bluetooth Antenna has been connected to the Antenna port of the inverter.
An Android or IOS mobile phone with Bluetooth function is available.
Soliscloud APP is installed on the mobile phone.
There are three ways to download and install the latest APP:
1. You can visit to download the latest www.soliscloud.com
version APP.
2. You can search “ ” in Google Play or App Store.Soliscloud
3. You can scan this QR code below to download " ".Soliscloud
User Manual