• Configure the WiFi stick for remote monitoring. Please
follow the instructions manual in the WiFi stick’s box.
STEP 6: Self-test in accordance with CEI 0-21 (Italy Only)
• The self-test is only required for inverters to be
commissioned in Italy. During the self-test, the inverter will
consecutively check the reaction times for: overvoltage,
undervoltage, maximum frequency and minimum
frequency.
• Please use the Soltaro APP to initiate the self-test
procedure and get the test results. Refer to Soltaro APP
Operation Instructions for details.
7.3 Decommission
STEP 1: Turn off the load;
STEP 2: Turn off the PV;
STEP 3: Turn off battery;
STEP 4: Turn off the main grid switch;
STEP 5: Wait for at least 5 minutes after the LED and graphical
display black out for the internal circuits to discharges energy;
STEP 6: Disconnect all the power cable;
STEP 7: Disconnect all the communication cable, Remove the
WiFi stick;
STEP 8: Remove the inverter from the wall, also remove the
bracket if necessary;
STEP 9: Pack the inverter with the original carton, and store it.