48
Follow all safety regulations when the
machine lifts objects.
z Don’t use damaged chain, wire rope, or
cord in lifting work.
z Don’t move the load suddenly, don’t move
load on the top of human beings, and never
permit anybody to be adjacent to the load.
z Ensure everybody is away from the lifted
objects until the chocks support the load
or the load has been stably placed on the
ground.
z Fix superstructure and place the
traveling motor at the rear.
Don ’ t connect sling/chain to the bucket
teeth.
3.6 LIFT WORK
Lifting hook mark:
750610020152
1) Sling/chain should tightly bind the load, the workman should glove when bind sling/chain.
2) Connect sling/chain with bucket lifting ring, curled bucket and retracted arm.
3) Before start, uniform the hand signal with signalman.
4) Acquaint with the positions of all workmen in the range of work area.
5) Mark hand rigging on the load to ensure the people pulling hand rigging is away from load.
6) Try to lift the load before normal operation.
z Park the machine beside the load.
z Load the machine.
z Lift load to the height of 50mm (2in) off the ground.
z While keeping the load close to ground, move the load from the machine.
z If there is any evidence of stability reduction, lower load to the ground.
7) Just lift the load to required height.
FIG.3-38