16 systemair
2.3 Assembly
2.3.1 Joining of unit modules
Delivertheshipmentunittoalocationascloseaspossibletothemountinglocation.Withamanualforklift,hoistthe
shipment unit so as to align its bottom with the foundation’s top surface.
Slide the shipment unit into its position on the foundation, using stripes or some other appropriate method. You may
need to apply heavy or extra-heavy furniture hauling trolleys.
Caution
Fastening connections are not intended for pulling the modules together. Pulling is done by means of
slings.
Tighteningisrequiredonthebottomoftheunitnearbaseframeorbottomproles.
Applysealingtapeontheshipmentunitsjoiningsurfaces(connectingproles).Slideandpresstheshipmentunits
togetherbymeansofslings.Werecommendslingswithbrackets,appliedsoastopreventdamagetothecasings.
Tighten the thread connections on all the joining elements.
[1] Joining of base frames
This should always be the primary connection.
There are several options for joining you can use with your unit:
1 Joining of base frames All units
2
Joining of corner
reinforcements
Larger units
3
Joining of vertical
reinforcements
Larger units
4
Joining of internal
connecting elements
(vertically and horisontally)
Depending on size and execution
5
Joining of external
connecting elements
(only vertically)
Smal units and depending on
execution
Fastening material
For each connection the following fastening material is always
supplied:
1x Screw DIN 933 Zn M8 x 70
1x Nut DIN 934 M8 Zn
2x Washer DIN 9021 8,4 Zn