Start Link Training
To start Link Training do the following steps:
1. From the Menu Bar select Analyze > Link Training.
2. Press the Arm button.
3. Start Link Training on the device under test (DUT).
Starting Link Training on the DUT is DUT-specific, but is typically done from a command line console program.
LinkTraining
DPO70000SX, MSO/DPO70000DX, MSO/DPO70000C, DPO7000C, and MSO/DPO5000B Series 213

Table of Contents

Other manuals for Tektronix MSO5104B

Questions and Answers:

Question and Answer IconNeed help?

Do you have a question about the Tektronix MSO5104B and is the answer not in the manual?

Tektronix MSO5104B Specifications

General IconGeneral
BrandTektronix
ModelMSO5104B
CategoryTest Equipment
LanguageEnglish

Related product manuals