Refrigeration Maintenance
116
Remove Evacuation Hoses
1. Run the Zone 1 and Zone 2 units in High
Speed Cool with the receiver outlet and
discharge service valves back seated.
2. Front seat the suction service valve and allow
the compressor to pump down to 3 to 5 psig
(21 to 35 kPa). Stop the unit. Remove the hose
from the suction service valve service port.
Immediately install the cap on the suction
service port and tighten it.
3. Back seat the suction service valve.
4. Remove the hoses from the receiver outlet and
discharge service valves.
5. Replace and tighten the service port and valve
stem caps.
6. The unit is now ready for a functional check
out and run in.
1. Front Seat to Pump Down
2. Back Seated
3. Back Seated
Figure 63: Remove Evacuation Hoses
2
1
3
AEA2088