TSC 80e TRANSFER SWITCH CONTROLLER
PM091 Rev 1 09/02/27 Thomson Technology
35
exercise test mode, the transfer switch will automatically re-transfer back to the utility
supply if the generator set fails. Refer to Section 4.2 for programming change
procedure.
The following sub-menus are located within this section:
4.6.3.1.Start Week
Select the week number (e.g. 1-4) that the generator set is to be started to
begin its exercise period.
NOTE:
Week Number is programmable only if the System Time
Clock Rollover period is set longer than 7 days.
4.6.3.2.Start Day
Select the day of the week (e.g. Monday, Tuesday, etc.) that the generator set
is to be started to begin its exercise period.
4.6.3.3.Start Hour
Select the hour of the day (e.g. 0-23 hour) that the generator set is to be
started to begin its exercise period.
4.6.3.4.Start Min
Select the minute of the day (e.g. 0-59 minutes) that the generator set is to be
started to begin its exercise period.
4.6.3.5.Run Time Hours
Select the number of hours (e.g. 0-23 hour) that the generator set is to be
operated during its exercise period.
4.6.3.6.Run Time Min
Select the number of minutes (e.g. 0-60 minutes) that the generator set is to be
operated during its exercise period.
4.6.3.7.Rollover Days
Select the number of days (7, 14, 21, 28) in which the system time clock will
rollover for desired operation of the exercise timer. (Example - If a weekly test