166
RT-SVX073A-EN
Trane Startup Checklist
This checklist is intended to be a guide for the Trane
technician just prior to unit 'startup'. Many of the
recommended checks and actions could expose the
technician to electrical and mechanical hazards. Refer to
the appropriate sections in the this manual for appropriate
procedures, component specifications and safety
instructions.
Important: This checklist is not intended as a substitution
for the contractorās installation instruction.
Important: Except where noted, it is implied that the Trane
technician is to use this checklist for
inspection/verification of prior tasks completed
by the general contractor at installation. Use
the line item content to also record the
associated values onto the Trane unitary
packaged equipment log.
Job Name Serial #
Job Location Model #
Sales Order # Ship Date
Unit DL # (special units) Date
Starting Sales Office Technician
Table 65. Startup checklist for S*HN, 90ā150 units
Complete
1
Crankcase heaters working for 8 hours prior to arrival of Trane technician performing startup
Yes No
2
Correct voltage supplied to unit and electric heaters
3
Unit exterior inspected
4
Disconnect all power, Unit interior free from debris/obstructions etc.
5
Open all access doors to verify all open and close fully without any binding
6
All wiring connections tight
7
Unit properly grounded
8
Copper power wiring meets sizing requirement
9
All field control wiring for CV, SZVAV or VAV controls completed
10
All automation and remote controls installed/wired
11
Unit clearances adequate for service and to avoid air recirculation etc.
12
For 120-150T units remove foam shipping blocks from evpaporator suction headers to allow proper condensate drainage.
13
All unit drain lines and traps proper
14
All coil fins inspected and straightened
15
Shipping hardware for compressors removed
16
Hold down bolts and channels from fan sections removed
17
Fan section spring isolators checked/adjusted
18
Damper linkages tight/adjusted
19
Rail connector splice brackets installed on low side base rail
Where applicable: Electric Heat
20
Electric heat circuits have continuity
Where applicable: Gas Heat
21
Gas heat piping includes drip leg previously installed by controlling contractor
22
Gas heat flue assembly fully installed
23
Gas heat condensate line + heat tape installed where applicable
24
Verify heating system matches the nameplate
25
Perform Gas Heat startup procedure in IOM
Where applicable: HW/Steam Heat
26
Modulating valve and actuator (HW and Steam) installed/wired
27
Steam heat swing check vacuum breakers installed per IOM direction
28
Steam heat condensate trap provided
29
O/A pressure sensor installed and piped
30
High side to low side piping to be completed prior to Trane technician arriving for startup
31
Space sensor and pneumatic tubing installed properly
32
Compressor discharge service valves, oil valves and liquid lines valves open/back seated (excludes Schrader valves)