Field Converting Horizontal Ductwork
(Supply or Return) from Right to the Left
Side
Figure 6. Ductwork conversion
Door
Header
Header
Panel 2
Header
Post
Door
Panel 1
Footer
Left
Side
Right
Side
As Shipped
(Right Side Hz)
Left
Side
Right
Side
Field Converted
(Left Side Hz)
Panel 2
Panel 1
To field convert horizontal ductwork from right side to the
left, follow this procedure:
1. Remove Panel 2 from end of unit
2. Remove the Door and Door header from the left side.
3. Assemble Door header and Door removed from the left
side in the empty location on the end wall.
4. Remove Panel 1 and Post from the left side. Remove
gaskets from the base rail flange at the bottom.
5. Remove the top duct adapter, side duct adapters,
header, and footer in this order from the right side.
Remove gaskets from post side flanges and the base
rail flange at the bottom.
6. Assemble gaskets, header, footer, side duct adapters,
and top duct adapter in this order to the left side.
SeeFigure 6, p. 27 for gasket application details.
7. Finally assemble Post, gaskets, Panel 1, and Panel 2 in
this order to the right side to complete the field
conversion. See Figure 7, p. 28 and Figure 8, p. 29 for
gasket application details.