22 RT-SVX34C-EN
Unit Dimensions and Weights
Unit Rigging and Placement
WARNING
Heavy Objects!
Do not use cables (chains or slings) except as shown. Each of the cables (chains or slings) used
to lift the unit must be capable of supporting the entire weight of the unit. Lifting cables (chains
or slings) may not be of the same length. Adjust as necessary for even unit lift. Other lifting
arrangements may cause equipment or property-only damage. Failure to properly lift unit may
result in death or serious injury.
Use spreader bars as shown in the diagram. Refer to the Installation manual or nameplate for unit
weight. Refer to the Installation instructions located inside the control panel for further rigging
information.
1. Verify that the roof curb has the proper gaskets installed and is level and square to assure an
adequate curb-to-unit seal.
The units must be as level as possible in order to assure proper condensate flow out of the unit.
The maximum side-to-side and end-to-end slope allowable in any application is listed in
Table 2, p. 23.