Veeder-Root TLS-350R PLUS - MAG-XL Flex Probe Installation; Pre-Installation Component Setup and Functional Check; Assemble the Battery Pack Mounting Bracket; Probe Installation - Manway 4-Inch Riser Pipe

Veeder-Root TLS-350R PLUS
38 pages
To Next Page IconTo Next Page
To Next Page IconTo Next Page
To Previous Page IconTo Previous Page
To Previous Page IconTo Previous Page
Loading...
15
MAG-XL Flex Probe Installation
Pre-Installation Component Setup and Functional Check
Follow the steps in the ‘Pre-Installation Component Setup and Functional Check’ section of the TLS RF Wireless 2
System (W2) Installation and Maintenance Guide (577013-964) to verify the Wireless Systems component
functionality.
Assemble the Battery Pack Mounting Bracket
PROBE INSTALLATION - MANWAY 4-INCH RISER PIPE
1. Connect the two 4-inch conduit hangers (item 1) from the installation kit to the battery mounting bracket (item
4) as shown in Figure 6.
2. Insert the bolt/nut pairs (items 2 and 3 in the figure) in each hanger as shown, but do not tighten.
3. Tighten the two bolt/nut pairs (items 2 and 5 in the figure) securing the mounting bracket to the conduit hang-
ers.
4. Get the customer supplied outdoor junction box. Get the customer supplied 3/4” x 1/2” reducing bushing.
Apply pipe thread sealant or PTFE tape to its threads and screw it into the top threaded opening of the junc-
tion box until tight.
5. Get the 1/2” nipple from the probe installation kit. Apply pipe thread sealant or PTFE tape to its threads and
screw it in the reducing bushing until tight.
6. Get the 1/2” brass hex adapter from the probe installation kit and after orienting the embossed arrow down,
apply pipe thread sealant or PTFE tape to its threads and screw it onto the 1/2” nipple until tight.
7. Take the battery support assembly, the junction box/conduit assembly and the transmitter to the top of the tank
for final assembly.
PROBE INSTALLATION - TOP OF TANK 2-INCH PIPE OPENING
1. Connect the two 2-inch conduit hangers (item 1) from the installation kit to the battery mounting bracket (item
4) as shown in Figure 6.
2. Insert the bolt/nut pairs (items 2 and 3 in the figure) in each hanger as shown, but do not tighten.
3. Tighten the two bolt/nut pairs (items 2 and 5 in the figure) securing the mounting bracket to the conduit hang-
ers.