Commissioning
9.2 Tests before commissioning
44
Operator’s Manual | APS | 5100060593 | 02/2022 | [en]
Ground conditions
The maximum dumping height depends on several factors of the ground
conditions. An exact specification of this value is not possible.
Determine the maximum fill height by compaction tests or soil
samples.
Shaking in cobblestones
To avoid damage to the machine or compaction material, use a slid-
ing device, see Accessories on page 57.
Compaction of asphalt
To avoid cracking and sticking to the asphalt, use water tank with
sprinkler system, see Accessories on page 57.
9.2 Tests before commissioning
Information
Further information and detailed descriptions, see Maintenance on
page 49.
Perform the following checks:
Check machine and components for damage.
Do not put the damaged machine into operation. Damages and
defects must be repaired immediately.
Check the charge state of the accumulator.
Check to ensure the screw connections are firmly seated.
Check control elements for functionality.
9.3 Charge the rechargeable battery
NOTICE
Damage to the machine or the accumulator.
Only use chargers and rechargeable batteries from the manufacturer.
NOTICE
Note on putting into operation!
Detailed and illustrated information can be found in the operator’s manual
of the battery charger.

Table of Contents

Questions and Answers:

Question and Answer IconNeed help?

Do you have a question about the Wacker Neuson APS1030 and is the answer not in the manual?

Wacker Neuson APS1030 Specifications

General IconGeneral
BrandWacker Neuson
ModelAPS1030
CategoryPower Tool
LanguageEnglish

Related product manuals