Instructions for Assembly
Item number 116519-0000 Subject to technical modifications
Version 4 23.04.2014 Page 10/47
Cassita II/Cassita II LED
3 List of Tools
Good tools are the key to ensuring productivity and making certain that the quality of the
assembly work is good. The following is a list of the minimum tools that we recommend you have
available for installing your weinor awning under “normal” building conditions
Tool Size Use
Tools/machines
Allen key SW 4
SW 6
SW 8
To set the projection for the free-
wheeling mechanism
To adjust the arm position on the
drop profile
To fasten the clamp part
To set the height adjustment for the
ceiling
To adjust the inclination
Open-end or ring spanner SW 19 To fasten the brackets
Phillips screwdriver 2 To mount the wall bracket cover caps
Power drill, bits To drill screw holes
Clamps
To tension the cord during rafter
bracket installation
Cable reel as required
Ladder as required
Measuring and testing tools
Tape measure
To measure the bracket position
To measure the installation height
and the width of the unit
Spirit level, rope or mason's cord To align the unit
Installation tools
Touch-up pencils
1)
For touch-up work
Pencils For tracing / marking
Test run cable To set/adjust the drive, for test runs
Protective clothing
Safety shoes To protect against falling parts
Protective gloves To protect against sharp edges on
profiles and components
1)
Supplied by weinor.