68 3064810_201804
35.Commissioningreport
Commissioningsteps Testvaluesorconrmation
1.) Serial number on the type plate
___________________________________
2.) Electrical wiring/connection/fuse protection checked in
accordance with technical data from installation instructions
and VDE regulations?
□
2.) Systemushed? □
3.) Systemlledandwatertreatmentcarriedoutinlinewith
"Technical information, water treatment"?
pH value set
Total hardness set
□
_______________ pH value
_______________ °dH
4.) Appliance and system vented? □
5.) System pressure 2.0 - 2.5 bar? □
6.) Water connections checked for tightness? □
7.) Traplled? □
8.) Gas valve set to gas type? Natural gas □
LPG □
Wobbe index _________________ kWh/m³
Caloricvalue,heating_________kWh/m³
9.) Gas supply pressure checked? □
10.) Gas tightness test carried out? □
11.) Switch boiler ON, set control unit to OFF/Standby. □