3064810_201804 79
37.Technicalinformation,air/uegas
routing
11
12
13
4
14
417
9
16
3
4
1
BalancedueinsideaductwithhorizontalconnectingpipeDN60/100
Flue gas < 110 °C
Installationexampleforbal-
ancedue/duct
C33x
Install horizontal
pipe with > 3°
slope towards
boiler
Please
note
1 Gascondensingboiler
3 Separator
(slide coupling)
if required
4 BalancedueDN60/100
500 mm
1000 mm
2000 mm
9 Inspectionbend
11 Pipe collar
12 Support rail
13 Support bend 87° DN60/100
14 Spacer
16 Ductcover with
UV resistant terminal
17 Spacerbracket