8. Installation
Initially, determine the location for the installation of the gas
condensing boiler.
For this, take into account the ue gas connection, lateral
clearances towards walls and the ceiling, and any existing
connectionsforgas,heating,DHWandelectrics.
Openingthecasingcover
We recommend you remove the casing cover during the
installation.
Release the casing cover with the l.h. and r.h. screw. Release
the bottom of the casing cover and unhook at the top.
Securingtheappliancewiththesuspensionbracket
Duringinstallationofthegascondensingboiler,
ensurethatallxingsarestrongenoughtocarry
itsweight.Alsotakeintoaccountthecondition
ofthewall,asanescapeofgasorwatermight
resultinariskofexplosionandooding.
Screws
Fig.: Undoing screws
Fig.: Drill holes for suspension bracket
Min. 446 mm
Ceiling
- Mark the holes to be drilled for the mounting bracket, taking
into consideration the minimum clearances.
-Inserttherawlplugsandtthemountingbracketwiththe
coach bolts and washers supplied.
- Hookthegascondensingboilerwiththemountingstaysinto
the mounting bracket.
Mounting stay
Fig.: Mounting brace on the condensing boiler
Aftercompletingservicing,closethefrontcasing
againandfastenthescrewstightly.Thereisa
riskofcarbonmonoxidepoisoningiftheue
systemisfaulty.