Inspection
Remove any transit packing and inspect the unit to  
ensure that all components have been delivered and 
that no damage has occurred during transit. If any 
damage is evident, it should be noted on the carrier’s 
freight bill and a claim entered in accordance with the 
instructions given on the advice note.
\Major damage must be reported immediately to your 
local Johnson Controls representative.
Moving the chiller
Before moving the unit, ensure that the installation 
site is suitable for installing the unit and is easily  
capable of supporting the weight of the unit and all  
associated services.
The unit must only be lifted by the base 
frame at the points provided. Never move 
the unit on rollers, or lift the unit using a 
forklift truck.
Care must be taken to avoid damaging the condenser 
cooling fins when moving the unit.
Unit removal from shipping container
1.  Place a clevis pin into the holes provided at the 
end of each base rail on the unit. Attach chains or 
nylon straps through the clevis pins and hook onto 
a suitable lift truck for pulling the unit out of the 
container.
2.  Slowly place tension on the chains or straps until 
the unit begins to move and then slowly pull the 
unit from the container. Be sure to pull straight so 
the sides do not scrape the container.
3.  
and reattach the chain or strap. Slightly lift the 
front of the unit to remove some weight from the 
       
with an operator on each side to guide the lift 
truck operator. 
4.  Pull the unit until the lifting locations are outside 
of the container. Place 4 X 4 blocks of wood under 
the base rails of the unit. Gently rest the unit on 
the blocks and remove the chains and lift truck.
5.  Attach lifting rigging from the crane and slowly 
complete the removal from the container then lift 
up and away.
LD19197a
Lifting using lugs
Units are provided with lifting holes in the base 
frame which accept the accessory lifting lug set as 
shown in Figure 4. The lugs (RH and LH) should be  
inserted into the respective holes in the base frame and 
turned so that the spring loaded pin engages into the 
hole and the flanges on the lug lock behind the hole. 
The lugs should be attached to the cables/chains using 
shackles or safety hooks.
Figure 4 -  Lifting using lugs
LOCKING PIN
LUG
FLANGE
LIFTING HOLE
IN BASE FRAME
CORRECT
LOCKING PIN
LUG
LIFTING HOLE
IN BASE FRAME
FLANGE
INCORRECT
LOCKING
PIN
FLANGE
LUG
LD19197b
Lifting using shackles
The shackles should be inserted into the respective 
holes in the base frame and secured from the inside.
•  Use spreader bars to avoid lifting chains hitting the 
chiller. Various methods of spreader bar arrange-
ments may be used, keeping in mind the intent is 
to keep the unit stable and to keep the chains from 
hitting the chiller and causing damage.
•  Never lift the chiller using a forklift or by hook-
ing to the top rails. Use only the lifting holes pro-
vided.
•  Lifting Instructions are placed on a label on the 
chiller and on the shipping bag.