SECTION 3 - HANDLING, STORAGE, INSTALLATION AND REASSEMBLY
LD17278
YORK
YORK
BY JOHNSON CONTROLS
2’ Min.
(610mm)
3’ -6” Min.
(1067mm)
End Sheet Clearance
Must be of a greater
Distance than the
Length of the Shell.
2’ Min.
(610mm)
FIGURE 8 - SERVICE CLEARANCE REQUIREMENTS
LOCATION
Locate the chiller in an indoor location with tempera-
ture ranges from 40°-110°F (4°-43°C) and adequate
ventilation that meets the all ANSI, state, and local
codes.
FOUNDATION
A level floor, foundation, or a customer supplied house-
keeping pad must be provided by the customer, which
is capable of supporting the unit operating weight.
CLEARANCE FOR SERVICE
To ensure adequate space for servicing the unit, adhere
to the following clearances as shown in Figure 8 on
page 28 for single and dual compressor conguration:
Rear and top of unit – 2 ft (610 mm)
Front of unit – 3 ft 6 in (1067 mm)
Tube removal (See Table 2 on page 28 for
Clearance)
TABLE 2 - SERVICE CLEARANCE REQUIRE-
MENTS
SHELL CODE
(PIN 5,7)
TUBE REMOVAL
SPACE
ADD MARINE
WATER BOXES
ft-in mm ft-in mm
B 10-1 3073 2-2 660
C 12-1 3683 2-2 660
D 14-1 4293 2-2 660
If optional shipping skids are used, remove them be-
fore lowering the unit to its mounting position. Use an
overhead lift to rig the unit to its final location on the
floor or mounting pad by lifting the unit, and lowering
it to its mounting position.