JOHNSON CONTROLS
73
SECTION 4 - TECHNICAL DATA
FORM 201.30-ICOM1 (519)
ISSUE DATE: 05/22/2019
4
DIMENSIONS
EVAPORATOR AND CONDENSER
SHELL CODES IN (MM)
SINGLE 145/151 DUAL 136/145
B-B C-C D-D M-M N-N
A 8ˊ (2438) 10ˊ (3048) 12ˊ (3658) 12' (3658) 14' (4268)
B 6ˊ-11/16" (1846) 6ˊ-11/16" (1846) 6ˊ-11/16" (1846) 6'-3/4" (1844) 6'-3/4" (1844)
C 4ˊ-7 5/8" (1413) 4ˊ-7 5/8" (1413) 4ˊ-7 5/8" (1413) 4'-7-5/16" (1405) 4'-7-5/16" (1405)
D 2ˊ-2 15/16" (684) 2ˊ-2 15/16" (684) 2ˊ-2 15/16" (684) 2'-2-7/8" (683) 2'-2-7/8" (683)
E 2ˊ-4 11/16" (729) 2ˊ-4 11/16" (729) 2ˊ-4 11/16" (729) 2'-4-3/8" (722) 2'-4-3/8" (722)
F 1ˊ-1 15/32" (342) 1ˊ-1 15/32" (342) 1ˊ-1 15/32" (342) 1'-1-3/8" (342) 1'-1-3/8" (342)
G 1ˊ-2 11/32" (365) 1ˊ-2 11/32" (365) 1ˊ-2 11/32" (365) 1'-2-3/16" (361) 1'-2-3/16" (361)
M 6ˊ 21/32" (169) 1ˊ-6 21/32" (474) 2ˊ-6 21/32" (779) 4-3/4" (123) 10-3/4" (275)
N 1ˊ-2 17/32" (369) 2ˊ-2 17/32" (674) 3ˊ-2 17/32" (979) 5'-6" (1678) 6' (1830)
WATER BOX DIMENSIONS IN (MM)
DIM.
EVAPORATORS B, C & D
EVAPORATORS
M, N
CONDENSER B, C & D CONDENSERS M, N
1 PASS 2 PASS 3 PASS 2-PASS 3-PASS 1 PASS 2 PASS 3 PASS 1-PASS 2-PASS 3-PASS
H —— —— —— —— ——
1ˊ-1
17/32"
(344)
1ˊ-1
17/32"
(344)
1ˊ-1
17/32"
(344)
14ˊ-1/2”
(369)
14ˊ-1/2”
(369)
14ˊ-1/2”
(369)
I ——
1ˊ-2 3/8"
(369)
1ˊ-2 3/8"
(369)
16-3/32"
(409)
16-3/32"
(409)
—— —— —— —— —— ——
DIM. REAR HEAD 2 PASS
REAR HEAD
2-PASS
REAR HEAD 2 PASS REAR HEAD 2-PASS
J —— 6ˊ-29/32" (176) 5ˊ-3/4" (146)
K 7ˊ-21/32" (195) 6ˊ-5/32" (156) ——
ADDITIONAL OPERATING HEIGHT IN (MM)
CLEARANCE TO FLOOR P
TYPE OF CHILLER MOUNTING
NEOPRENE PAD ISOLATORS 1-3/4” (44.5)
SPRING ISOLATORS 1”DEFLECTION 1” (25.4)
DIRECT MOUNT 3/4” (19.1)
NOTES:
1. All dimensions are approximate. Certied dimensions are available on request.
2. Evaporator and condenser water nozzles can be located on either end of unit.
3. Standard 150 PSI (10.3 barg) design pressure boxes shown.
4. To determine overall height, add dimension “P” for the appropriate isolator type.
5. Front of unit is dened as side of chiller where control center is mounted.
6. In order to achieve rated performance, condenser liquid must enter the water box through the bottom connection for
proper operation of the sub-cooler.
7. Connected piping should allow for the removal of the compact water boxes for tube access and cleaning.