CHAPTER 6
Post-installation check list
Make sure that the system date was set properly using the CoreSense web interface.
Make sure that the thermal pump is enabled (see “Administration settings” on page 36). While the
thermal pump is disabled, the SYSTEM LED is yellow.
Make sure that the hydrogen and moisture WARNING and ALARM limits have been configured
properly for your application.
Perform a visual inspection of the installation. Check for oil leaks.
Verify that cable glands are properly tightened and secured.
Make sure that the CoreSense is appropriately grounded.
Was PTFE applied on the 1.5 NPT fitting, as per “Installation on transformer valve” on page 15?
Make sure that the eight bolts for the CoreSense rotating flange are secured with the proper torque,
as described in “Installing the sensor head” on page 15.
Make sure that the two bolts for the CoreSense external sampling cover are properly secured.
Did you install/replace the o-ring that seals the CoreSense enclosure?
Verify that the 4 retaining screws of the CoreSense enclosure are properly secured.
Verify that the system, hydrogen and moisture LEDs are green.
Dispose of any collected oil according to your company regulations and local laws.