PCM600 is used for various tasks in the protection relay engineering process.
Relay engineering management
Organizing the bay protection relays in the structure of the substation by
defining voltage levels and bays below the substation. PCM600 manages
the project.
Configuring the parameters and setting values for the protection relay itself
and for the process functions by using the Parameter Setting tool.
Configuring the events shown on the LHMI using the HMI Event Filtering
tool.
Reusing configurations from older protection relay versions using the
Configuration Migration tool.
Communication management
IEC 61850 station communication engineering is done using the internal
IEC 61850 Configuration tool or the separate IET600. PCM600 interacts
with IET600 by importing and exporting SCL files.
Configuring the GOOSE receiving data connections to the protection
relay's application configuration function blocks by using the Signal Matrix
tool.
Configuring protocol data mapping for Modbus with the Communication
Management tool.
Record management
Generating overviews on the available (disturbance) recordings in all
connected protection relays by using the Disturbance Handling tool.
Manually reading the recording files (in the COMTRADE format) from the
protection relays by using the Disturbance Handling tool or automatically
by using the PCM600 Scheduler.
Managing recording files with the Disturbance Handling tool.
Creating recording file content overview reports for fast evaluation with
assistance of the Disturbance Handling tool.
Using the Fault Record tool to read fault records from the protection relay,
save records to a PC and clear old records.
Service management
Monitoring the selected signals of a protection relay for commissioning or
service purposes by using the Signal Monitoring tool and Event Viewer tool
(including audit trail).