ABB | SACE Emax 2
Mechanical characteristics
1 - E1.2 description
151 | © 2023 ABB | 1SDH001330R1002 - ECN000297030
Manual operations for opening
and closing the circuit-breaker
The following is the sequence of steps for closing and opening the circuit-breaker:
1. Check that the circuit-breaker is open (open / closed indicator "O - OPEN"), and check that the
springs are discharged (spring signalling device "white - DISCHARGED SPRING") as indicated in
Figure 42.
2. Charging the springs - Pull the lever [A] downwards several times until the springs charged
signalling device [B] is “yellow - CHARGED SPRING” as indicated in Figure 43.
Figure 42
A
B
Figure 43
3. Check that the circuit-breaker is open (open/closed signalling device “O - OPEN”), and check that
the springs are charged (springs signalling device “yellow - CHARGED SPRING”) as indicated in
Figure 44.
4. Closing - Press the closing pushbutton “I - Push ON” as indicated in Figure 45.
Figure 44
Figure 45
5. Check that the circuit-breaker is closed (open/closed indicator "I - CLOSED"), and check that the
springs are discharged (spring signalling device "white - DISCHARGED SPRING" as indicated in
Figure 46.
6. Opening - Press the opening pushbutton “O - Push OFF” as indicated in Figure 47.
Figure 46
Figure 47
Continued on the next page