31
LS-10 Load Shelf
This option is used as a support shelf for the product to
avoid the bag from prematurely tearing off at the perforation
when the product is inserted in the bag. The Load Shelf
allows the product to drop onto the shelf relieving the
pressure on the bottom of the bag. See Figure 3 - 7.
To turn ON the load shelf, press the <Load Shelf> menu
option and press the <ON> button. The Load Shelf down
time is the length of time the shelf is in the down position.
Note: Increase time for longer bags.
FS-10 Flat Seal Assembly
Fingers enter the bag immediately before sealing to pull the
front/back layer of bag together, decreasing wrinkles or
folds. Figure 3 - 8.
To turn the Flat Seal Assembly ON, press the <Flat Seal>
button on the Options menu and toggle ON the ON/OFF
button. Use the <Setup> button to make it easier to
mechanically adjust the fingers along the front plate slots
on the T-1000. Once the mechanical adjustment is
complete, press <ON> and <AUTO> for normal operation
of the flat seal assembly. In the Auto mode, the option will
operate automatically.
FS-30 Heavy-Duty Flat Seal Assembly
There are two separate motions:
1. Fingers enter the bag and start to pull the sides of
the bag outward
2. Both of the fingers extend sideways with regulated
pressure to pull the sides outward, further decreasing
the opportunity for folds or wrinkles in the seal area.
In Setup Mode, the button operations are:
<OFF> Position: Fingers Up and Out
<SETUP> Position: Fingers Down and Out
<HOME> Position: Fingers Down and In
During Seal Cycle, fingers go to the “OFF” position when Seal Time starts, and before Index. This is to prevent
fingers from interfering with next bag moving forward. See Figure 3 - 9.