44 1200 Series Quarternary Pump User Manual
3 Installing the Pump
Priming and Purging the System
Priming and Purging the System
If a degasser is installed, it can be primed either by drawing solvent through
the degasser with a syringe or by pumping with the pump.
Priming the vacuum degasser or system with a syringe is recommended, when:
vacuum degasser or connected tubings are used for the first time or vacuum
tubes are empty or
changing to solvents that are immiscible with the solvent currently in the
vacuum tubes.
Priming the system by using the pump at high flow rate (3–5 ml/min) is
recommended, when:
pumping system was turned off for a length of time (for example, overnight)
and if volatile solvent mixtures are used, or
solvents have been changed.

Table of Contents

Other manuals for Agilent Technologies 1200 series

Questions and Answers:

Question and Answer IconNeed help?

Do you have a question about the Agilent Technologies 1200 series and is the answer not in the manual?

Agilent Technologies 1200 series Specifications

General IconGeneral
BrandAgilent Technologies
Model1200 series
CategoryLaboratory Equipment
LanguageEnglish

Related product manuals