Installing SFP Transceivers
To install an SFP transceiver, perform the following procedure:
Note
The transceiver can be hot-swapped; you do not need to power off
the switch to install a transceiver. However, you should always
remove the cables before removing the transceiver.
Note
You should always install the transceiver before connecting the
fiber-optic cables to it.
1. Remove the transceiver from its shipping container and store the
packaging material in a safe location.
Warning
An SFP transceiver can be damaged by static electricity. Be sure to
observe all standard electrostatic discharge (ESD) precautions,
such as wearing an antistatic wrist strap, to avoid damaging the
transceiver.
2. Remove the dust plug from an SFP slot. See Figure 12.
Figure 12. Removing the Dust Plug from an SFP Slot
3. Position the SFP transceiver with the label facing up.

Table of Contents

Other manuals for Allied Telesis AT-GS900M Series

Questions and Answers:

Question and Answer IconNeed help?

Do you have a question about the Allied Telesis AT-GS900M Series and is the answer not in the manual?

Allied Telesis AT-GS900M Series Specifications

General IconGeneral
BrandAllied Telesis
ModelAT-GS900M Series
CategorySwitch
LanguageEnglish

Related product manuals