Installation & Start-Up | 3-1
INSTALLATION AND STARTUP
Unpacking and Inspection
Remove components from the packing case(s) carefully; check contents against packing list.
Inspect all components for obvious damage and broken/loose parts or ittings. Notify the
carrier and AMETEK Service (1-800-537-6044) immediately if parts are missing or damage
is found.
Sample System Space Requirements
Explosion-proof enclosure - approximately 50 x 30 x 43 cm plus clearance for analyzer con-
nections. Refer to Figure 3-6.
Power Requirements
The System is shipped according to the customer order and is fused and set for the voltage
of the required mains power. The power requirements are stated on the metal plate on the
side of the casting and in the speciication section of analyzer manual.
System Tubing
Recommended system tubing is 1/8 inch OD, electro polished, 316 stainless steel meeting
ASTM #632 speciications (AMETEK PN 257707000 or equivalent).
Dry Reference Gas
A dryer (AMETEK Dryer PN 305400901S or equivalent) is required to dry reference gas to
less than 0.025 ppmv.
A dryer (AMETEK Dryer PN 305617901S or equivalent) is required to dry the gas to less
than 0.01 ppmv for zeroing the 3050-SLR.
Dryers must be periodically replaced. In normal use, the dryer (PN 305400901S) should
dry a 50-ppm reference gas to speciication for 1 year.