11.2 PRE-START PROCEDURES & CHECKS
24
The system is level.
The system is installed on a concrete plinth or stable
capable of sustaining weights in excess of 400kgstructure
A minimum distance of 300mm is present above the system, to allow the lid to be
removed for maintenance (see section 5.3 Air Flow).
A minimum distance of 600mm is present on the fan discharge side and 150mm on

A minimum distance of 50mm is present between the exterior of the tank and wall for
air circulation and servicing (see section 5.3 Air Flow).
The condensate drainage elbow has only been hand tightened
(see section 8.0 Plumbing Installation).

connected to the PTR or any other line (see section 8.0 Plumbing Installation).
The unit is connected to either a Continuous 24 hour supply or a Shoulder Tariff
Minimum 16 hour supply. (not connected to the Off-peak 8-10 hour supply.
The plumber has explained the purpose of the tempering valve.
Once the system has been installed, the installing plumber should sign below
to ensure that all procedures have been complied to otherwise warranties
may be voided.