Use the sling-rigged method to lift large detectors into a vertical position while they are still crated. Use this method
to position while they are still crated. Use this method to position large detectors vertically into pipelines.
Figure 3: Sling-Rigged Lifting Methods
Do not lift a detector with a forklift by positioning the detector body on the forks, with the flanges extending beyond
the lift. This could dent the housing or damage the internal coil assemblies.
Never place forklift forks, rigging chains, straps, slings, hooks or other lifting devices inside or through the detector's
flow tube to hoist the unit. This could damage the isolating liner.
Do not lift detector with forklift. Do not lift or rig lifting devices through detector.
Figure 4: Lifting and Rigging Cautions
User Manual
Page 7 September 2013