Connecting the locating current injector
29
EDS309x_D00012_03_M_XXEN/11.2014
5.4 Connection to a PV system
Connect the locating current injector PGH186 as follows:
Legend:
PGH186 Locating current injector
AGE185 Coupling device
EDS3096PV Equipment for insulation fault location
EDS195P Insulation fault locator
PSA30.. Measuring clamp (locating current sensor)
EDS-SET BNC Tee connector and 2 BNC cables for fault localisation in diode-decoupled systems
Risk of electric shock!
On touching live uninsulated conductors, death or serious injury may be caused.
For this reason prevent any physical contact with active conductors and follow
the rules for working on electrical systems.
Risk of electric shock!
If the PGH186 is connected using terminals L1(+) und L2(–) to a system that is live
due to its operation, the terminal must not be disconnected from the protec-
tive earth conductor (PE). Otherwise the terminal will be at the dangerous system
voltage!
Risk of short circuit!
When the EDS3090PV is connected with test leads without integrated fuses a
short circuit may occur due to incorrect wiring. Connect the EDS3090PV with the
accompanying test lead with integrated fuses to reduce the risk of a short circuit.
Central inverter
=
AGE185
PGH186
PE
E
L1(+)
L2(-)
IT system
Transformer
EDS
195P
BNC
EDS
195P
BNC
EDS
195P
BNC
Junction Box
PSA30..
PSA30..
PSA30..
EDS-
SET
Insulation
fault
Strings
PSA30..