9. Handing over of the installation
!
Review and service should be performed by authorised
personnel only.
• Make repeated start attempts to ensure that the adjustments
function.
• Close the ball valve during operation to check that the gas switch
switches off at the set value.
• Remove the hose for the air pressure switch to check that the burner
locks out.
• Check that all protective covers and measurement nipples are
mounted and fastened.
• Fill out necessary test reports.
• Instruct the persons in charge of the operation on the service and
maintenance of the installation and what to do should any troubles
occur.
• Inspection and service must be carried out by authorized personnel.