Commissioning
8
ekr CON 600, ekr CON 600 net – Application with Wide Array Edge Sensors 27/39
8.2 Requirements
The web guiding system has been fully wired up, i.e. the cable
connections between the separate web guiding components
(controller, sensors, actuator, ...) have been made.
The controller is connected to the power supply.
All transport locking devices on the guiding device and actuator
have been removed.
8.3 Performing the Material Setup
In order to achieve optimal guiding results, you have to carry out a
material setup during the initial commissioning of the web guiding
system (see Performing the Material Setup, page 32).
During the material setup the controller is automatically adjusted
to the properties of the material to be scanned.

Other manuals for BST ekr CON 600 net

Questions and Answers:

Question and Answer IconNeed help?

Do you have a question about the BST ekr CON 600 net and is the answer not in the manual?

BST ekr CON 600 net Specifications

General IconGeneral
BrandBST
Modelekr CON 600 net
CategoryController
LanguageEnglish

Related product manuals