2-2 Installation
3902 Service Delivery Switch Hardware Installation and Start-up Manual
009-3205-001 Standard Revision D
Copyright
©
2013-2015 Ciena
®
Corporation July 2015
Installation Overview
Installation of the 3902 involves the following high level steps:
1 Mount the 3902 on the installation surface. See “Mounting the 3902” on
page 2-3 for more information.
2 Install the power supply. See “Installing the Power Supply” on page 2-4 for
more information.
3 Install an SFP in the NNI port. See “Installing the SFP” on page 2-4 for
more information.
4 Install cabling to the ports on the faceplate. See “Installing the Interface
Cabling” on page 2-5 for more information.
You have installed the 3902.
WARNING
Do not work on the system or connect or disconnect cables
during periods of lightning activity.
WARNING
Do not stack anything on top of this unit.
WARNING
The 3902 relies on the AC power cord for the Safety Ground.
The outlet providing power to the 3902 must meet the Local
and National Safety codes.