Loading System MkII Assembly
23
If using Precast Kentledge as the ballast option, please proceed to step 3. If
using cast concrete as the ballast option, please proceed to step 4 and if
using gravel as the ballast option, please proceed to step 5.
3. Precast Kentledge ballast option
Check that the two rear Corner Posts are inserted correctly, and the two
front Corner Posts are left to one side. Use a forklift truck to place two
800 kg COMBISAFE Precast Kentledge onto the Bottom Frame, see
Figure 16. When the concrete block is in place, place the two remaining
Corner Posts into the Bottom Frame. Next step is to mount the top unit,
please proceed to step 6.
Figure 16. Placement of last ballast.
4. Cast-In-Concrete ballast option
4.1 Check that all four Corner Posts are inserted correctly into the Bottom
Frame. Cut a piece of 18 mm Formwork Plywood, complying with EN
636-3, in the format as shown in Figure 17 and place in the centre of the
Bottom Frame. Bolt the eight Formwork Supports to the welding nuts
located on the Corner Posts. Use the bolts attached to the Formwork
Supports, see Figure 18. At this step it is not necessary to tighten the
bolts.